|

Bisha Project Eritrea
Update
March 5, 2007
BISHA PROJECT ERITREA Update
Nevsun
Resources Ltd. (NSU-TSX and AMEX) (“Nevsun”)
is pleased to provide an update on steps
taken to date to progress the application
for a mining license at its Bisha Project in
Eritrea. As previously reported,
January 17, 2007, the Government of Eritrea
has been actively reviewing the Feasibility
Study, the Social and Environmental Impact
Assessment (SEIA), and the draft
Environmental Management Plan for the Bisha
project. These documents were prepared on
behalf of the Company by AMEC Americas for
the purpose of licensing the Bisha Project.
The Government of Eritrea engaged an
international mining consultancy to complete
a due diligence review of these documents,
and Nevsun requested Endeavour Financial to
arrange a further independent review to be
completed on behalf of prospective project
financing partners.
Since January
2007 with the two due diligence reviews in
progress, the Company has continued
constructive discussion with the Government
of Eritrea regarding the development of a
mining agreement with a view to taking the
Bisha Project into production. These
discussions are still progressing. In early
February H.E. Tesfai Ghebreselassie, the
Minister of Energy and Mines of Eritrea,
outlined the continuing strong government
support for exploration and mine development
in Eritrea, including the Bisha Project, in
a presentation at the Indaba Conference in
Cape Town.
In parallel
with the mining agreement discussions,
Nevsun is progressing with the selection
review for an EPCM (engineering,
procurement, construction and management)
contractor for the Bisha Project. The
Company has also sought competitive quotes
for the procurement of the project’s major
capital long lead items. The main critical
long lead items include the crusher, SAG and
ball mills, mill motors and mining fleet.
The Company is planning to order the most
critical long lead items shortly so as to
enhance a timely completion for the overall
project. Funding for this procurement and
for starting the detailed engineering design
component of an EPCM contract for the 2m
tonne per year Bisha mining and milling
operations was the focus of the private
placement financing of October, 2006.
The technical
and financial details of the Bisha Project
were included in the press release of
October 12, 2006 and a Technical Report was
filed both on Sedar and on EDGAR in November
2006. News releases can be found on the
Company’s web site (www.nevsun.com) as
well
as on Sedar at
www.sedar.com and EDGAR at
www.sec.gov/edgar/searchedgar.
A project
summary is presented below.
Life of
Mine Metal Production - Payable - 1.06
million oz gold
- 747 million lb copper
- 1,092
million lb zinc
- 10 million
oz silver
Production
Schedule - + 10 years open pit mine
modeled at 2 Mt/year of ore production
- years 1 and
2, average 447,000 oz Au per year
- years 3 to 5 average 173 million lb Cu per
year plus precious metal credits
- years 6 to 10 average 218 million lb Zn
plus 39 million lb Cu per year plus precious
metal credits
Bisha is a
high grade gold, silver and base metal-rich
volcanogenic massive sulphide (VMS) deposit.
The feasibility study indicates that the ore
can be mined and processed using industry
standard technology. The study indicates
that the existing road infrastructure in
Eritrea will be suitable for the project.
Project infrastructure development will
require construction of a power plant at the
project site and construction of a
concentrate storage and loadout facility at
the port of Massawa, Eritrea.
The
Deposit
The Bisha
deposit is configured in three distinct
layered zones – a 35m thick surface oxide
zone having a high gold and silver content
immediately overlying a 30m thick copper
enriched supergene zone which itself
overlies a primary sulphide zone containing
both zinc and copper. Significant byproduct
gold and silver are recoverable from both
the supergene and primary ores.

Processing
Processing
of the three ore types will utilize a common
crushing and SAG/ball grinding circuit, but
will require three different extraction and
processing circuits. After grinding, gold
and silver will be extracted from the oxide
ore by conventional cyanide leaching and
recovered by the carbon in pulp process.
Later in the project the supergene and
primary ores will be processed by a
conventional flotation process to recover
copper and zinc as concentrates for direct
sale to smelters. The tailing systems will
be common for all three ore types.
The
feasibility study envisages the mining and
processing of each zone in succession
starting with the surface oxide zone.
Before the oxide ore is exhausted the copper
flotation process equipment will be
installed and commissioned so that a smooth
transition can be made from oxide ore to the
supergene ore treatment. Similarly, before
the supergene ore is exhausted, the
additional flotation equipment required to
recover the zinc from the primary ore will
be installed and commissioned to permit a
smooth transition from supergene to primary
ore. No interruption to production is
anticipated or required when transitioning
from one ore type to another.
Opportunities
As with most
projects at the feasibility study stage,
both risks and opportunities exist. Comments
on the risks of the industry can be found
below in our forward looking statement.
Opportunities that could significantly
enhance the project include:
1)
Expansion of mining to an underground
operation as the Bisha deposit is open at
depth;
2)
Metal prices - at current commodity
prices, modeling of the known deposit,
including inferred resources, demonstrates a
potential additional 8 years mine life as a
result of enlarging the pit and going to
depth;
3)
Development of additional deposits
already identified through exploration (Harena
and Northwest Zone);
4)
Additional indicated primary sulphide
resources that have not been included in the
estimate of reserves have been identified
(which mostly lie within the waste envelop
of the Bisha open pit). Approximately 4.7
million tonnes of 1.15% copper were
identified after the start of the
development of the mining study. The
Company has disclosed the above under news
release dated January 10, 2006,
5)
A near surface hanging wall copper
zone has been discovered at the western
margin of the open pit, as defined by drill
intersections of 2.11% Cu over 19.6 m and
2.64% Cu over 12.0 m. This zone may have the
potential to be added to the resource in the
future.
Forward Looking
Statements: The above contains forward
looking statements that are subject to a
number of known and unknown risks,
uncertainties and other factors that may
cause actual results to differ materially
from those anticipated in our forward
looking statements. Factors that could
cause such differences include: changes in
world commodity markets, equity markets,
costs and supply of materials relevant to
the mining industry, extent of resources
actually contained in mineral deposits,
actual recoveries achieved in processing
ore, technological change, weather
conditions, change in government and changes
to regulations affecting the mining
industry. Forward-looking statements in
this release include statements regarding
future programs, review completion dates and
opportunities. Although we believe the
expectations reflected in our forward
looking statements are reasonable, results
may vary, and we cannot guarantee future
results, levels of activity, performance or
achievements.
| NEVSUN RESOURCES
LTD.
“John A. Clarke”
Dr. John A. Clarke
President & Chief Executive Officer
NSU07-02 |
For further information, Contact:
Judy Baker
(604)
623-4704 or
(416) 786-7860 or 1-888-600-2200
e-mail:
nevsuninfo@nevsun.com
Website:
www.nevsun.com |
|