|
Scoping Study Completed for Bisha
Project in Eritrea

December 6, 2005
Nevsun
Resources Ltd., (NSU-TSX/AMEX) is pleased to
announce the results of the scoping study
completed for the Bisha project in Eritrea
by AMEC Americas Limited (AMEC), an
international engineering company. The
initial drill hole that made the Bisha
discovery was completed by Nevsun in
November 2002. Upon discovery, an extensive
exploration and drill program was completed
at the Bisha project, a volcanogenic massive
sulphide deposit with a gold-rich gossan cap
(see figure 1). The scoping study
commissioned by Nevsun in the spring of 2005
for the Bisha Main deposit has now been
completed and the following is a brief
summary. All dollar amounts are in $US.
The pre-tax
and pre-financing project economics as
presented in the scoping study are shown
below using both current commodity prices
and conservative historical commodity
prices. At current commodity prices, the
Bisha project has a net present value
pre-tax and pre-financing of US$ 1.3 billion
and an IRR of 71%. The AMEC base case (using
more conservative historic prices) as
outlined below reduces the NPV to US$346
million and the IRR to 35%. A final
feasibility study is due for completion in
mid 2006.
|
Economic Scenarios
|
Commodity Price Scenario |
0%
Discount NPV |
IRR |
Payback Period |
|
Current Commodity Prices (Nov 30/05)
|
Gold US$ 495/oz
Copper US$ 1.99/lb
Silver US$ 8.27/oz
Zinc US$ 0.76/lb |
US$ 1.3 B |
71% |
1.3 years |
|
Conservative Historical Commodity
Prices
(AMEC Base Case) |
Gold US$ 400/oz
Copper US$ 1.05/lb
Silver US$ 6.00/oz
Zinc US$ 0.50/lb |
US$ 346 M |
35% |
1.9 years |
The Company
has presented the Bisha scoping study to Mr.
Tesfai Ghebreselassie, the Minister of
Energy and Mines of Eritrea. Mr.
Ghebreselassie stated: “We congratulate
Nevsun on its exploration success, and we
look forward to continuing the Ministry’s
cooperation and partnership in developing
the world class Bisha deposit into a
producing mine”.
The scoping
study mine plan is based on the indicated
resources included in the 2004 Bisha Main
geological model evaluated by AMEC (see
press release of October 18, 2004) and
metallurgical test work completed by S.G.S.
Lakefield conducted during spring 2005 on
representative core drilled and collected
under the supervision of AMEC staff.
The 2004
Bisha Main resource is presented below.
|
|
Cut-off
|
Tonnes
m |
Au g/t |
Ag g/t |
Cu % |
Zn % |
|
Indicated |
|
|
|
|
|
|
|
Oxides |
0.5g/t Au |
4.99 |
6.51 |
30.00 |
0.10 |
0.08 |
|
Supergene Cu |
0.5% Cu |
7.65 |
0.46 |
35.56 |
3.47 |
0.87 |
|
Primary |
2.0% Zn |
1.71 |
0.74 |
29.59 |
0.97 |
3.07 |
|
Primary Zn |
2.0% Zn |
8.41 |
0.76 |
58.27 |
1.12 |
9.04 |
|
Total tonnes |
|
22.76 |
|
|
|
|
|
Inferred |
|
|
|
|
|
|
|
Oxides |
0.5g/t Au |
0.12 |
3.34 |
18.20 |
0.12 |
0.07 |
|
Supergene Cu |
0.5% Cu |
0.19 |
0.09 |
30.14 |
3.26 |
1.04 |
|
Primary |
2.0% Zn |
0.39 |
0.75 |
35.20 |
1.24 |
3.03 |
|
Primary Zn |
2.0% Zn |
5.15 |
0.70 |
59.67 |
0.84 |
8.28 |
|
Total tonnes |
|
5.85 |
|
|
|
|
The estimated
open pit mineable material derived from this
resource and presented in the scoping study
is as follows:
|
Ore |
Tonnes
m |
Au g/t |
Ag g/t |
Cu
% |
Zn
% |
Au
recovery |
Ag
recovery |
Cu
recovery |
|
Oxide |
4.1 |
7.6 |
35.8 |
0.1 |
0.1 |
87% |
45% |
|
|
Supergene Cu |
6.3 |
1.0 |
41.1 |
4.1 |
0.5 |
42% |
64% |
85% |
|
Primary |
3.1 |
0.7 |
36.2 |
1.4 |
1.8 |
Concentrate recoveries are:
83%
copper and 85% zinc |
|
Primary Zn |
7.0 |
0.8 |
59.2 |
1.2 |
9.4 |
|
Total
tonnes |
20.5 |
|
The scoping
study used a rate of production for the
Bisha project of 2 million tonnes of ore per
annum providing for a 10 year open pit mine
life. A further study will be required to
evaluate the further underground potential
of the Bisha Main deposit to take production
beyond 10 years. The primary sulphide ore
widths at the base of the open pit are
typically greater than 50m in width and
could provide significant potential for a
long life underground operation.
Preproduction
capital has been estimated at US$156 million
(including a 20% contingency factor) for a
mining fleet, a gold leach plant, tailings,
water storage and water diversion dams,
equipment maintenance facilities, an
administration building and an operations
camp and owner’s costs during construction.
The scoping
study effectively presents three mines in
one to reflect the three distinct ore types
of the Bisha Main deposit. The first two
years of operation is as a gold mine
processing the high grade oxide ores. The
next three years of operation is as a copper
mine processing the supergene copper ores
that underlie the oxide ore zone. From year
six onwards primary sulphide ores that lie
immediately below the supergene ores are
processed to generate separate copper and
zinc concentrates.
In the first
two years of operation as a gold mine the
process plant is fed exclusively with oxide
ore in a traditional SAG mill/ball mill
configuration using leach and CIP for gold
and silver recovery. During these first two
years a flotation plant to process the
supergene copper ores will be installed and
a copper concentrate shipping facility will
be completed at the Port of Massawa for a
combined estimated cost of US$38 million.
These additions will allow the same crusher
and mills initially installed for the oxide
ore processing to convert to sulphide ore
processing. At no time will mixed oxide and
sulphide ores be processed.
In year five,
a zinc flotation plant and an expansion of
the storage facilities at the port will be
completed for an estimated cost of a further
US$20 million. This will permit the
continued long life operation of the Bisha
plant and infrastructure processing primary
sulphide ores to produce separate copper and
zinc concentrates through sequential
flotation for shipping and delivery to the
international smelting market. During year
six supergene sulphide ores and primary ores
will be campaigned separately through the
process plant as the open pit develops to
depth into the primary sulphide ore zones.
The open pit
has an estimated pit depth of 220m which
will be mined in stages as a series of pit
shells. The mining strip ratio (waste to
ore) is approximately 2:1 for the first two
years (oxide ores), is approximately 4:1 for
the next three years (copper supergene ores)
and approximately 5:1 for the following five
years (predominantly primary sulphide ores).
Full details on the final infill drill
results for the completed Bisha Main deposit
drill program were published in a news
release on July 11, 2005. The completion of
this drill program permitted the start of a
new evaluation of the Bisha Main resource as
an integral part of the development of a
final mining program and reserve estimation
for the ongoing Bisha feasibility study.
This new resource estimate is expected to be
published in January 2006.
Bill Nielsen, Vice-President of Exploration
for Nevsun, a qualified person under
National Instrument 43-101, supervised and
directed all work associated with the
drilling program.
Nevsun Resources will host a Conference Call
to discuss the Scoping Study for the Bisha
Project in Eritrea on Monday, December 12th
at 11 a.m. Eastern time, 8 a.m. Pacific
time.
The Conference Call Dial-In Numbers are:
1) North America 1-877-691-0878
2) International
1-973-582-2773
Confirmation Number: 6788592, or state “Nevsun
Resources - Bisha Scoping Study Update”
Webcast access for
registration is
http://viavid.net/dce.aspx?sid=00002BD5
. This information is posted on the Nevsun
website,
www.nevsun.com/events.html.
Forward
Looking Statements: The above contains
forward looking statements that are subject
to a number of known and unknown risks,
uncertainties and other factors that may
cause actual results to differ materially
from those anticipated in our forward
looking statements. Factors that could cause
such differences include: changes in world
commodity markets, equity markets, costs and
supply of materials relevant to the mining
industry, change in government and changes
to regulations affecting the mining
industry. Although we believe the
expectations reflected in our forward
looking statements are reasonable, results
may vary, and we cannot guarantee future
results, levels of activity, performance or
achievements.
Forward-looking statements are frequently,
but not always, identified by words such as
“expects,” “anticipates,” “believes,”
“intends,” “estimates,” “potential,”
“possible” and similar expressions, or
statements that events, conditions or
results “will,” “may,” “could” or “should”
occur or be achieved.
| NEVSUN RESOURCES LTD.
“John A. Clarke”
Dr.
John A. Clarke
President & Chief Executive Officer
Nsu05-32.doc |
For further information,
Contact:
Judy Baker (416)786-7860
other Nevsun
contact numbers:
(604) 623-4704 or 1-888-600-2200
e-mail:
nevsuninfo@nevsun.com
Website:
www.nevsun.com
|

Figure 1. Bisha Main Deposit
|