|
Tabakoto Update

TABAKOTO UPDATE
April 21, 2005
Nevsun
Resources is pleased to confirm that the
Tabakoto Mine construction program is
targeted for a production start during third
quarter 2005. The Company has been awaiting
confirmation from MDM, the engineering
contractor for Tabakoto, of the successful
shipment of major capital goods and supplies
from South Africa and from Europe before
publishing this estimate. It is anticipated
that following commissioning the production
rate will be stepped up at Tabakoto to full
capacity of 105,000 ounces of gold per year
within 3 months of start-up.
The
construction decision was made in May 2004
without any required bank finance or gold
hedging.
Major
shipments of engineering goods and
fabricated construction material for
Tabakoto commenced in March with the sailing
of the Vessel Arjan on March 8th
from Richards Bay in South Africa to Dakar
(arrived Dakar on March 28th). A final
vessel is being arranged by MDM. The
Tabakoto ball mill, a Polysius mill
fabricated by Krupp in Germany, arrived in
Dakar from Europe on April 15th and will be
carefully transported to site. Most of the
equipment and supplies for the Tabakoto
project are shipped to Mali via Dakar,
Senegal and transported by road or rail
through to Kayes in Western Mali, and then
by road to Tabakoto.
The
Company has reported, in its recently
published AIF, that the current estimate for
the combined pre-production and capital cost
for the Tabakoto Mine is US$45m. This
estimate represents additional costs of
approximately US$5m, a reflection of
increases in international steel costs,
freight costs, and South African Rand/US$
exchange rates. The Tabakoto feasibility
study provided an average annual production
rate of 105,000 ounces of gold per year
milling 650,000 tonnes per year of ore. The
plant has been designed with some
flexibility for future expansion
opportunities including the over sizing of
the crusher capacity at 1,200,000 tonnes of
ore per year. Expansion for mining Nevsun’s
neighboring Segala deposit will be evaluated
during the first year of operations. If the
Segala deposit is brought on line,
production would increase by approximately
50% per annum. If developed later, Segala
would extend production by four years. Other
satellite deposits and underground potential
at both Tabakoto and Segala could also
result in increased ounces produced per
year.
Pre-stripping at Tabakoto commenced December
2004 under a mining contract with BCM, a
contract mining company based in Ghana, that
operates throughout West Africa. Tabakoto
site facilities are well advanced.
Completion of electrical power generators
and fuel farm installations are due in early
June. Power will be supplied to the Tabakoto
mine as an ‘across the fence’ power supply
contract with Cummins Engineering. Fuel
supply will be managed at site by Shell. All
major supply contracts for the mine are in
place and delivery of major stores
inventories including reagents have
commenced. The on-site assay laboratory
service will be managed by Abilab, who run
their main assay facilities in Bamako.
Nevsun’s operations in Mali are managed
jointly by Denis Gregoire (General Manager,
Tabakoto Mine) on site and by Pierre Matte
(Manager Administration and Finance), who is
based in Bamako. The Mine Manager, Jan
Jansen, joined the team at Tabakoto in
September 2004. Recruitment is in progress
for various other site management and
production staff.
Bringing Tabakoto into production is a key
step in transitioning Nevsun from an
explorer to a mine developer. Nevsun’s
strategy is to continue building and
developing production operations centered on
its exploration successes in order to fully
return value to shareholders.
As
previously reported, Nevsun has engaged AMEC,
an international engineering company, to
conduct the feasibility study for its Bisha
high-grade gold/copper/zinc project in
Eritrea. Bisha is currently anticipated to
be in production during 2008. The
metallurgical core work is currently being
evaluated at SGS Lakefield. The Company
intends to further strengthen its management
team in preparation for developing the Bisha
project.
Forward Looking Statements:
The above contains forward looking
statements that are subject to a number of
known and unknown risks, uncertainties and
other factors that may cause actual results
to differ materially from those anticipated
in our forward looking statements. Factors
that could case such differences include:
changes in world commodities markets, equity
markets, costs and supply of materials
relevant to the mining industry, change in
government and changes to regulations
affecting the mining industry.
Forward-looking statements in this release
include statements regarding positive
indications of development of the Tabakoto
Gold Project and Bisha Project. Although we
believe the expectations reflected in our
forward looking statements are reasonable,
results may vary, and we cannot guarantee
future results, levels of activity,
performance or achievements.
|
NEVSUN
RESOURCES
LTD.
“John A. Clarke”
Dr.
John A. Clarke
President & Chief Executive Officer
Nsu05-13 .doc |
For
further information, Contact:
Maureen Carse
(604) 623-4700 or 1-888-600-2200
e-mail:
nevsuninfo@nevsun.com
Website:
www.nevsun.com |
|